Oct 18 – New Plan for Concrete Pour

The installation of the rebar will take longer than was first planned. Rather than 1 day, it is now expected to take 2 1/2 days. As a result the rebar people will be done Wednesday morning and the inspections will take place on Wednesday afternoon. The pour of the concrete for the retaining wall footing is now planned to start at 8:30 on Thursday morning.