Mar 19 – Drywall, Hardie plank and deck surface

Lots of activity going on, The drywall people have boarded all of the upper floor and several of the lower bedrooms. They will be mudding for next week or so. Then the painter will need to do the undercoat and first coat of finish paint. This is a slight delay from what our builder had expected so we pushed floor installation back to the week after Easter.

Our builder’s crew have been installing the Hardie plank on the north and west side of the building. We decided to add a belly band to breakup the Hardie plank. The belly band will be painted the same colour as the trim.

The deck people worked the weekend installing the deck surface.

We met with a railing supplier on Saturday and will be getting a quote for our railings on Monday.