On Tuesday, July 25th, we were expecting to have the septic tanks installed. The installer came in the morning and dug a big hole for the septic tank.
While he was working the plumbers came a day early to finish installing all the fixtures and the water filter systems. When the septic tank supplier showed up with his huge truck to deliver the first of two tanks it made for a very busy place.

Unfortunately after the tank was lowered into the hole, it was discovered that it had a defect. It was then loaded back on the truck and returned to the manufacturer for repaired. The tank will be repaired and recertified and this week. he septic system installer had to fill the hole back in because it would be safe to leave it open.
We will attempt to install the tanks on Monday July 31. Since the Elgin blocks for the field were delivered today, our installer should be able to start on the field soon after.