Jan 25 – Second Floor Retaining Wall Form Done

The second floor retailing wall form has been completed and the plan is to do the pour tomorrow morning. The road will be closed from 7:30 until 11:30 am. Thanks to John Gregg for the picture.

We just received the BC Surveyor’s Certification of Location of the Foundation, along with the bill. We also received word that the windows and external doors are complete and can be delivered at any time.