Oct 3 – Excavation Continues (much longer than expected) Posted on October 3, 2016 by admin They started digging the hole for the house and discovered that, according to the Geo-tech, all the material down to the water table must be removed and replaced with new rock. This will cost significantly more in terms of money and time.