Oct 31 – Retaining Wall and Footings Rebar Installed

header

Today the rebar people came in to start the installation of the rebar in the bottom floor retaining wall and footings forms. The rebar people should finish this part of their work tomorrow. Then the lake sideĀ of the retaining wall form needs to be completed and the forms inspected. The current plan is to pour the bottom floor retain wall and footings next Monday.