Sep 17 – Railings Complete Other Than Glass

On Friday, with the help of two of our friends (Jim Gerbrandt and Ted Staunton) concrete slabs were put under the stair that lead from the deck to the south yard. The railing installer then spent Saturday installing the railings on the stairs.

On Sunday, he completed the rest of the railings.

The railings will be complete after the glass panels have been inserted into the railing frames around the upper deck which is planned to happen this week. The only things that we know we need to do before the final inspection are a little bit of electrical work and do a walk through with our builder and have him address a the things that we have noticed.